The UNFCCC website contains a list of the 1799 issuances that took place sofar.
The time between end of monitoring period and the issuance has risen to 300 days [median]. Of these 300 days, the project developer needs about 30 [waiting for the final data to become available, writing monitoring report]. The remaining 9 months are spent in the verification and the UNFCCC system. The monitoring reports of the last issuances were written 6 - 9 months ago; new Executive Boards procedures introduced in the last few months may further slow down the issuance process.